Step 1 โ€” Element Details

New Pour Card
๐Ÿ“
Click to attach BBS PDF / DXF
Accepts .pdf ยท .dxf ยท .dwg ยท From TEKLA / CadBro / BBS Excel export
Fields marked * are required. The Sales Order is the commercial anchor โ€” all M-Books and RA Bills trace back to it. The BOQ item auto-filters by element type and grade. BBS drawing attachment is mandatory for all reinforced elements โ€” site engineers access it during pre-pour checklist verification.
Calculating for:
โœ“ Pour 1 of 3 Billed
โœ“ Pour 2 of 3 M-Book done
โ–ถ Pour 3 of 3 Active

Pour Card Header โ€” Pour 3 of 3

PC-2026-03-031 (draft)
Tata Networking
SO-TN-2026-001
Column ยท B3โ€“B5
M25
RCC-COL-M25-BLKC
4.50 m โ†’ 6.80 m (2.30 m)
3 of 3
STR-COL-22-R2
โœ“ BBS_COL-B3.pdf View โ†—

๐Ÿงฎ RMC Volume Calculator

Pour 3 of 3 ยท M25

Element dimensions (from drawing)

DescriptionNo.L (m)B (m)H (m)Vol (mยณ)
Main grid columns 3.11
Core columns 3.22
Net concrete volume 6.33

RMC order recommendation

Net volume
6.33
mยณ (calc)
+ Wastage
0.32
mยณ (5%)
+ Pump loss
0.50
mยณ
Order qty
7.50
mยณ (rounded)
No. of trucks required
2
2 ร— 7 mยณ = 14 mยณ ordered ยท Last truck partial
๐Ÿงช
IS 456 Cl.15.2 โ€” Cube sampling
For 7.50 mยณ โ†’ 1 set ร— 4 cubes minimum required on site.
๐Ÿ“Š
BOQ cumulative impact
RCC-COL-M25-BLKC: Previous 138.50 mยณ + this pour 7.50 mยณ = 146.00 mยณ of 220.00 mยณ BOQ. Balance: 74.00 mยณ (33.6% remaining).

Billing cycle โ€” Column B3โ€“B5 (all 3 pours)

Shows how each pour maps to billing. Pour 3 (this card) will be billed in the next RA Bill cycle after M-Book submission.
Pour 1 of 3
PC-2026-03-018
24 Mar 2026
Net: 6.12 mยณ
โœ“ RA Bill #12
โ‚น54,774 billed
Pour 2 of 3
PC-2026-03-025
30 Mar 2026
Net: 6.44 mยณ
M-Book MB-2026-044
Queued โ†’ RA Bill #13
Pour 3 of 3 โ† This card
PC-2026-03-031
08 Apr 2026 (planned)
Est: 7.50 mยณ ordered
๐Ÿ• Pending pour
โ†’ RA Bill #14 (future)
How partial billing works: Pour 2 M-Book is already submitted โ†’ it will be included in the next RA Bill cycle. Pour 3 has no M-Book yet (pour not done) โ†’ it stays out of billing until the pour happens, post-pour is recorded, BOQ split is confirmed, and M-Book is submitted. No special flag needed โ€” the system only bills locked M-Books.